I have tried to create delivery again, though I know it is fully delivered to check the error Error: No delivery-relevant items in order 0000943525, order type Z2K Z2K is the order type used to create sales order through EDI I have a order with 3 EA quantity and it is fully delivered, with order status is completed in document flow, delivery status is fully delivered both at item and header status tab but in schedule line tab it is showing 2 schedule line below 2016-07-22 3 3 2 EA 2 CP 2016-10-04 0 0 1 EA 1 CP So second schedule line is inconsistent as it showing future date, but actually order is fully delivered, please suggest Best Regards Abdullah
Why do you believe the schedule line is still "open"? I'm confused ... There are two lines, both are delivered in full (see delivered quantity), all document statuses are complete. So what exactly is the issue? The date in the schedule line? Well, that doesn't mean a lot anymore since it's already delivered. That date was what ATP thought would be the availability date, but I guess someone found a secret stash somewhere and managed to ship earlier.
The extra documents with zeroes in the document flow seem odd to me too but I guess it could be batch split or something. Either way, all items are complete and look OK to me from the status standpoint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Jelena,
Thanks a lot for your input, I think you are correct because document flow is showing as completed status also in schedule line tab we can see order qty 3 and delivered qty 3 but schedule line is in future, it is correct that someone able to manage a stock to ship earlier.
Thanks again for your inputs
Best Regards
Abdullah
Abdullah Taj Mohammed Shaikh wrote:
but schedule line is in future, it is correct that someone able to manage a stock to ship earlier.
It's the question for your business, not for SCN. We don't know what the acceptable business practice is for you and we don't know why exactly the goods were shipped earlier.
From the technical standpoint there is nothing in SAP to prevent such early deliveries and there might be a legitimate reason to deliver early (e.g. you could get an early shipment from the vendor or another order got cancelled making the goods available). Whether it's something that business users should be doing is another question for the company to address internally.
Share the screen shot of schedule line and document flow for that line item
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi G. Laksmipathi,
Thanks for the quick reply, we are following the standard process but while processing the delivery we have customized picked and packed process with Handling unit. Also shipment and invoice are showing twice because delivery is split into two batches 9001 and 9002 may be it is reason we can see two times invoice and shipment they are same.
Abdullah
User | Count |
---|---|
91 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.