on 08-11-2016 8:48 AM
Hello,
In ECC work center check the APO resource tab that External Capacity is aactive
and CFC9 check the setting for Use Ext. Capacity should be set to A when you want to transfer capacity to APO.
Refer consulting note 674838 - Resource transfer from APO Release 4.0
Best Regards,
R.Brahmankar