Time conflict in planning when changing FB date.

former_member245015
Discoverer
0 Kudos

Hello.

I have a question.

Time conflict in planning when changing FB date.

(1) I copy FWO 2500008876. (So I created FWO 2500008877)

(2) Create FB.(6200016137)

 

(3) You change Planned Departure Date and Planned Arrival Date.

( Planned Departure Date : 2015/03/03 -> 2015/05/05 )

(Planned Arrival Date     : 2015/04/04 -> 2015/06/06 )

  

(4) Then Error Right occured.

(5) and FU have problem(Time Conflict in Planning.)

If you have any idea or solution,

Please answer the question.

Thanks.

Ji-hoon.

Accepted Solutions (0)

Answers (2)

Answers (2)

NiteshSaluja1
Advisor
Advisor
0 Kudos

Hi Ji-hoon,

This message generally appears when the:

1. Acceptable Dates on FU and FB are not within the desired range.

2. If there is a Stage Date and Time conflict. for e.g. If the End date of 1st stage is after the Start date of 2nd stage(main stage) of activities.

Also as mentioned by Bimal, there are many SAP notes in this area. Do check on them as well.

Hope it helps.

BR//

Nitesh

Bimal_S
Active Participant
0 Kudos

In stages tab for each of the stages there are four dates each for pick and delivery.

Start Date (Acceptable): 

Start Date (Requested): 

End Date (Requested):  

End Date (Acceptable

Please share all of these. Time conflict happens because of the dates present here. BTW please share the TM version and SP level. There were many SAP notes on this area in previous TM releases.