on 08-09-2016 11:35 AM
Hi,
We are planning to have Forecast, Supply planning (using optimizer run) and Demand Supply Balancing for a Demo in IBP 6.0. Can we use S&OP Module or will we require IBP Supply module as well?
Would highly appreciate if someone can provide some clarity on this topic.
Thanks,
Samiksha
For Optimizer Supply Module would be needed from 6.0 onwards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Samiksha
currently i am workink on IBP supply on 6.2 , if you want i can discribe some tips that you will use to do one scenario of supply.
Jorge
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.