on 08-05-2016 2:41 PM
Hi Friends,
I am running a initial load on STXL Table. The Table has 400 million records to copy. I am planning to schedule 5 Calculation jobs in parallel.
Here are my settings,
in table IUUC_PRECALC_OBJ my entries are -
conv object- STXL
NUMREC 83152227
in table IUUC_PERF_OPTION my entries are -
tabname - STXL
PARALLEL JOBS - 5
SEQNUM - 20
READING TYPE 5
I see only 1 access job is running, I even tired to trigger the Access job from MWBMON but they got finished within 1 sec, there is nothing in log.
Can you please let me know if i am missing any setting ?
Hi,
Did you check if the BTC work processes are free in the source and the SLT systems.
Thanks
Alok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Gokul,
I just noticed you posted it in wrong forum.
This forum is for the SAP Landscape Transformation Software (SAP LT) which is used for SAP data transformations (conversions & migrations). I think your query is for data replication with SAP Landscape Transformation Replication Server (SLT). By the way SLT is used for the data replication (could be Real time or non-real time) sourcing from SAP or non-SAP systems into HANA.
For SLT, here is the forum - http://scn.sap.com/community/replication-server
Thanks
Alok
User | Count |
---|---|
98 | |
11 | |
11 | |
10 | |
10 | |
8 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.