on 08-03-2016 5:22 AM
We have ECC 6 with EHP 7. It does not have the standard pricing procedure J1NA01 for returnable packaging processing. Is there any other way I can do the rent settlement for the returnable packaging?
Hi,
you can use the General Pricing procedure also for the Returnable Packaging
the Packing material have LEIS in the item category group and you have Two sales Document types for the Process