WBS BOM at PR level

Former Member
0 Kudos

Hi All,

How to get WBS BOM on PR as I have created 'external activity' and assigned material on which PR was created so my requirement is get multiple material on single PR. As I can have WBS BOM on activity so same I need WBS BOM on PR so can anyone tell me how can I achieve this requirement from SAP standard.

Regards,

Faizan

Accepted Solutions (0)

Answers (2)

Answers (2)

kenmelching
Active Contributor
0 Kudos

Are you doing a BOM transfer to PS?

What material did you attach to the Network Activity as a component?  Was it the BOM Header material?

Shubham1
Employee
Employee
0 Kudos

Hi

I think you need to go for an internal activity.

How to create a PR for BOM from a Project (WBS,... | SCN

Above useful thread can be referred.

-Shubham