on 08-02-2016 6:51 AM
Dear All,
We are planning to upgrade PPM 5.0 to 6.01, I need few information which will be helpful to make certain decisions. Please find below the clarifications,
Current system details :
1. ECC6, EHP5
2. NW 7.0 Ehp2
3. PPM is installed on separate instance.
4. PPM - PS,FICO,HR integration ECC.
Query :
1. Do we need to upgrade to EHP7 for ECC or we can use the existing EHP5 ?
I have checked the latest Installation master guide from service market place but at few places in document its confusing, so wanted to check from fellow consultant who have come across this scenario.
Regards,
Kumar
Hi,
please just have a look at the list I provided above, case (1) and (6) are the cases for stand-alone installation.
Regards,
Florian
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Aditya & Florian,
Thanks for the inputs, I also checked there is a ABAP add on component CPRXRPM 610_740 to get this installed in PPM 6.01 we need EHP7 or EHP8 ERP6.
As stated earlier PPM5.0 is installed separate instance so still do we need to go for EHP7 ERP 6?
Regards,
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Can anyone please help me on this its real urgent.
Regards,
Kumar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Kumar,
Whenever upgrading, you can always check the compatibility at support.sap.com/pam.
If I understand your requirement correctly, check the following PAM for PPM 6.0 product version.
As you can see, you will have to upgrade the NetWeaver to 7.3 or 7.4; That means you are looking at ECC EHP5.
Hope this helps.
Best Regards,
Aditya Kotak
Hi,
regarding prerequisites for 6.1, please always see SAP Note
2026407 | FAQs - SAP Portfolio and Project Management 6.1 |
There you'll find:
-------------------------------------------------------------------------------------------------
Installation options:
SAP Portfolio and Project Management 6.1 (ABAP) is released for installation only on
(1) SAP NetWeaver 7.4 with SAP Business Suite Foundation 747
stand-alone (i.e. without ERP, CRM, SCM, or SRM)
or
(2) SAP NetWeaver 7.4 with SAP Business Suite Foundation 747
plus SAP ERP 6.0 Enhancement Package 7
(EhP 7)
or
(3) SAP NetWeaver 7.4 with SAP Business Suite Foundation 747
plus SAP CRM 7.0 Enhancement Package 3
or
(4) SAP NetWeaver 7.4 with SAP Business Suite Foundation 747
plus SAP SCM 7.0 Enhancement Package 3
or
(5) SAP NetWeaver 7.4 with SAP Business Suite Foundation 747
plus SAP SRM 7.0 Enhancement Package 3
or
(6) SAP NetWeaver 7.5 with SAP Business Suite Foundation 748
stand-alone (i.e. without ERP, CRM, SCM, or SRM)
or
(7) SAP NetWeaver 7.5 with SAP Business Suite Foundation 748
plus SAP ERP 6.0 Enhancement Package 8
(EhP 😎
or
(8) SAP NetWeaver 7.5 with SAP Business Suite Foundation 748
plus SAP CRM 7.0 Enhancement Package 4
or
(9) SAP NetWeaver 7.5 with SAP Business Suite Foundation 748
plus SAP SCM 7.0 Enhancement Package 4
or
(10) SAP NetWeaver 7.5 with SAP Business Suite Foundation 748
plus SAP SRM 7.0 Enhancement Package 4.
-------------------------------------------------------------------------------------------------
I have highlighted the relevant cases for using it on top of ERP.
Kind regards,
Florian