Hello Experts
we are facing an issue with the requirements availability dates not aligned properly in a chronological order in RRP3. For example, if we have a process order available on 08/03/2016 and a Purreq due on 08/01/2016, the process order appears before the purreq as oppose to pureq appearing before the process order because its availability date is before the process order. Any advice would be greatly appreciated. Thank you
can anyone help me with this issue, please?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi MIK APO,
Are you in Continuous Input/Output scenario? If yes, please, check what is the Continuous Scheduling Date of the Process Order - in case it is earlier than Avail/ReqD of the PurRqs, that is the reason.
If you are not in Conti-I/O scenario, please, check whether there is an implementation of BAdI /SAPAPO/RRP_IO_COL changing the sequence of elements.
Regards,
Tiago