on 07-27-2016 11:40 AM
HI
I am confused about how a "spot price" for a Shipment can be passed to a shipment cost document.
1. maintain a separate condition record valid for a short period of time so this is picked up in Shipment Costing
2. enter the price manually in shipment cost document .. (but this is generally created some days later after Shipment Completion stage)
We would really like to enter the price in the shipment as this is some days before the Shipment Cost doc is being created? .. or similar solution?
Thanks
You have already indicated the available options. Either you maintain condition record with short validity period or have the option to enter manually in shipment cost document.
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.