on 07-27-2016 11:25 AM
Hi Team ,
I configured Substitution Rules for WBS like
PROJ-PROFL = '0000001' AND PRPS-POSKI :16-16: = 'N'
AND PROJ-ERDAT >= '01.10.2000' and also in project profile Configuration Substions auto check is there
but while saving WBS Substitutions are not working .
So i have checked substitution Configuration if i delete this part AND PROJ-ERDAT >= '01.10.2000' from Prerequisite
substitutions are workinf fine .
Can you please let me know better condition here .
HI ,
The issue is solved now ,
the condition for substitution rule should write for save and after save condition .
( ( PROJ-ERDAT = '00000000' ) OR ( PROJ-ERDAT >= '20160730' ) )
Regards,
ashok.V
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.