on 07-26-2016 8:11 AM
Hi Experts,
In my project, Controlling area currency is SAR and object currency is USD.
For 4 projects value in object currency is not appearing correct in CJ31.
For example- WBS XXXX is showing value in controlling area curreny as 375 SAR so in object curreny value should display as 100 USD but in system , object currency value is appearing as 375*3.75= 1406.25
This error is coming for few projects only. rest of projects are shwing correct value.
Please suggest .
Thanks & Regards
Singh AK
Hello Singh AK,
It looks to me that the wrong value in object currency seems relevant to currency translation.
Please refer to note 906975 on currency translation on budgeting and see whether you have the right exchange rate maintained.
Best regards,
Miya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Singh,
Check budget project profile t code : OPS9 normally, CJ31 will pick currency based on your selection criteria.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
102 | |
14 | |
10 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.