on 07-21-2016 8:42 AM
Hello
For certain routes we have fixed goods issue dates, for example loading on Monday and Friday for transport to Spain.
Is there a possibility to have these dates as fixed dates in SAP?
From the same shipping point we do have other dates for France or other countries.
These fixed dates would help us to respect the routes and calendars we have and for transport to see these dates on their correct lists.
Thanks
Kathleen
This function is called Route Schedule and illustrative in Route Schedule - Supply Chain Management (SCM) - SCN Wiki
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Juergen
This is not exactly what we are looking for as this seems to be calculating back from the delivery date, we would like to have another possibility, to have fixed loading dates, so for example every Monday and Friday for delivery to all ship-to's in Spain, knowing they all have different delivery dates.