on 07-18-2016 11:14 AM
Hi all,
Before posting this query i have searched the forum but didn't get the solution.
For a client I am using Billing plan ( Periodic) , and they have to bill the resources according to the days. They need to create order with reference to the contract.
So when created a contract , and also gave the billing plan , the data is getting copied as it is,
1. All the data getting copied as it is except the billing dates , for that i have to give the start and the end date again in the order and it is not getting copied as it is from the contract.
2. now if i am removing one bock , and try to bill it is allowing me to do the billing
, however when i am removing two blocks from billing plan it is not allowing me to create the invoice and gives the error " 000010 Date 000015 is blocked for billing (billing plan)"
Asked me to check the log:
Thanks
What billing date has been proposed for the first one and what billing date was coming for the second one?
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.