Message no: BP601 Ntwk actvty budget exceeded

former_member1013626
Participant
0 Kudos

Dear friends,

    I got the below message at the network of the WBS.

The report S_ALR_87013558 shows budget is available.

May I know where the error is coming from?

Thanks,

Regards,
Kumar

Accepted Solutions (0)

Answers (4)

Answers (4)

shareeq_hussain
Active Participant
0 Kudos

Hi,

I have the same problem.  Funds Management not activated but still we are getting the error.

If rectified kindly share the solution.

Regards,

Shareeq

Former Member
0 Kudos

Hi Kumar,

Can you please check the tolerance limit of budget?

And then check, what is message type set for budget check i.e whether it is error, warning or information.

Thank you.

Sandeep

miya_wang
Active Participant
0 Kudos

Hello Kumar,
Please check in CJ31 instead of S_ALR_87013558 and see how much available budget you have. Then compare with the amount that you want to consume.

If the available budget shown in CJ31 is larger than the amount that you want to consume, please also run analysis report BPFCTRA0 for your project and input =SUM in the command field to see whether the assigned value is up to date.

Best regards,
Miya

MTerence
Active Contributor
0 Kudos

Hi Kumar,

What is the currency of the project ?

Are you adding material or service in the project ?

Regards

Terence

former_member1013626
Participant
0 Kudos

Dear Maria,

  The currency is SAR and the budget is in SAR as well. The activity is a service.

Regards,
Kumar

MTerence
Active Contributor
0 Kudos

Hi,

In such case, how much you are posting ?

Regards

Terence