Hi Experts,

We are facing a typical issue due to system document flow inconsistency during cancellation of Warehouse Task for an ODO Item.

We are working on EWM9.2 with SP:002

Scenario:

My ODO#1  Quantity is 100

Step1: Create the warehouse task for full Qty/ partial qty of the ODO Item. System successfully generate the warehouse tasks.

Step2: Cancel Warehouse Tasks.

On cancellation of Warehouse Task, I should able to generate the task again right.

Neither we could able to new Create Warehouse Tasks or not able to Adjust the Quantities to Zero for delivery closing.

But due to the system inconsistency the Document Flow of the ODO item is not updated for DocCat: TOR(Cancel Warehouse Task).

How do we correct this document flow inconsistency. Is there any SAP Note available.

Kindly let me know please.

Thanks & Regards

Ramesh.R

Accepted Solutions (1)

Accepted Solutions (1)

Hi!

First check smq2 and sm12.

If ok use utility /scwm/chm_prf

If don't help correct table /scdl/db_df

BR, Alex.