Hi experts

I'm trying to create a credit memo from QM02..followup is working, and header data are being transferred.

But i would like to transfer also the delivery items in assigned objects.

Any ideas?

Best regards

Marco

Accepted Solutions (0)

Answers (1)

Answers (1)

holger_hartung
Contributor
0 Kudos

Hi Marco,

how do try to create a credit memo? Do you use activity list or via menu -> notification -> functions -> sales order??

former_member196079
Active Contributor
0 Kudos

Hi Holger

yes...it's exactly what i do....to create new credit memo i go to: menu->notification->functions->sales order

regards

Marco

holger_hartung
Contributor
0 Kudos

Hi Marco,

for that way you can only use customizing for setting this function.

I recommend to use a function modul via activity list for more felxibility and induvidual setting. (as reference you could use QM06_SALES_ORDER_STOCK)

former_member196079
Active Contributor
0 Kudos

Hi Holger

Thanks for your reply.

How can i customize this FM?..i create a Z copied by your suggested one, then?how can i use that?

best regards

Marco

holger_hartung
Contributor
0 Kudos

Hi Marco,

now you can implement this FM to the activity list: QCC0 -> notification -> additional notification functions -> activity task

If you need more induvidual seetings in FM itselft, you need to implement ABAP coding.