Hi All,

We are using SAP PO 7.5 in our landscape with Linux and Oracle.

We are in phase of adding few new interfaces in our landscape And got details of messages/day from different teams.

We are expecting almost 10K new message to be going through SAP PO and thinking if we need to add any additional App server/RAM to our existing system to support our new messages without any performance delay..

I am looking for some guidance here like how can we correlate new messages or interface to identify for required hardware resources.

Please suggest.

Regards,

Shivam Mittal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Shivam,

Please refer to Section 3 of the below document:

https://support.sap.com/content/dam/library/SAP%20Support%20Portal/keys-systems-installations/system...

Additionally you can run the quick-sizer tool for SAP PI (as per my knowledge it is not yet released for SAP PO). More details can be found at Sizing of PO Server | SCN

Thanks,

Manas

Answers (1)

Answers (1)

former_member227283
Active Contributor
0 Kudos

Hi shivam,

Do you have sizing result for your existing PO setup ? How is your current utilization of existing production server.

When you say 10K message, how is the message frequency flow. Does 10K process in 1 hour or in 24 hours ?

Regards,

Anil