Hi,
We want to disable Material Components planned value addition into the Activity's and Project's Planned total.
If we plan a Material for an Activity, the Planned value reflects as follows:
Planned Material:
Activity's Planned Value (CTRL+F11):
Project Planned Value (as in S_ALR_87013532 and CJ31):
We want that just the Costs Activity's inserted Amount to be taken into consideration:
Right now, we see we can make this happen if we manually uncheck the "CostRel" (Relevancy to Costing) checkbox on the Material Component:
But we want that behavior to be taken by default.
Is there any costumizing/SPRO route that we can take to achieve this or something similar?
Thanks a lot for the help!!
Leo
Hello,
In the past I have tried for a long time to find standard ways for achieving exactly what you are needing. Unfortunately I did not find a standard solution and the standard system always determined the state of the field "CostRel" based on the parameters explained in the notes mentioned above by Terencce.
Finally I concluded that it is impossible to run away from customer-exits or BAdIs and exit "EXIT_SAPLCOMK_011" could do the job well. This exit is in principle not intended to change fields in the material component, but rather just to validate them. Nevertheless I believe that changing fields without many dependencies like the field "CostRel" should not harm.
As inside this exit the material component data is in principle not modifiable you would have to get the reference of structure RESBD from program SAPLCOMK using field symbols (something like assign ('(SAPLCOMK)RESBD') to <fs>) and then unset field SANKA in case it is set. Also in order for the change in field SANKA to be kept after saving it is also necessary to set field SANKA_CHG.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Do you need a pre defined amount on cost activity as planned amount? Then from where would the actual cost come from for this material?
Do you just want to project higher plan cost and the material cost as actual cost?
I first felt you needed non valuated stock in projects.
What is the business scenario?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
As per my assumption always value comes by costing variant but not dependently because costing variant required some source then SAP reccommand valuation variant assign to costing variant with customised parameter.
with the help of FICO consultant and business concept user. so check what you want to do?
Regards,
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sanjeev,
Thanks for your reply.
I can't get your point.
Do you have a transaction or SPRO path where to make the configuration change you are suggesting?
For this case, I am the one that makes the configuration changes, and am asking where I can change the configuration that would produce the desired effect.
Thanks a lot,
Leo
Hi Leo,
Refer below note to understand about this fields standard setup
677169 - FAQ 2: Material and Project System
533207 - Valuated and nonvaluated project stock
There can be multiple ways on achieving it.
1. Enhancement to check on save to remove the check
2. Screen variant SHD0
In case if any alternate way available wil update this thread.
Also kindly note this indicator is related to BOM
Regards
Terencce
ONe way is inform the material status in Material master data to avoid cost calculation. If you don´t have this option, is possible create a new status just regarding cost calculation (OMS4).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Access MM02;
Look the vision Basic Data; field Status Matl (to look the material in the entire environment)
Or
Vision MRP1
Field Matl. Status (to lock the material just in the plant)
Choose the appropriate Code Status (if you don´t know what the code status does, take a look in the customizing - OMS4).
Hi,
Check in OKK4, by changing the Valuation variant - 001 Planned Variant - Remove the priority
Create a new project and check
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
With OKK4, I got to change the Valuation Price taken from the Material Master Data. That was by changing the sequence on "Material Val" tab, at Valuation variant 010, "Network: Planned" (Tried 001, "Planned Valuation: Mat." but it doesn't change behavior).
Until now, the only that changes is the Price taken into consideration, but I can't choose to live it black, with no Strategy. If I select a Price that has no value, then the system throws the following error:
This lets one save the Project, but it's not a desired outcome.
Putting 0.01 USD at Planned Price 1, 2, or 3 seems wrong approach to me. Any input?
Thanks as always!
User | Count |
---|---|
101 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.