Hi,

Looking for some suggestions/solutions on Re-alignment in IBP wherein we would like to copy forecast values across planning combinations that is the forecast value for Same Key Figures from one product to another product. For example, copying Sales qty from Product A to Product B.

Accepted Solutions (0)

Answers (6)

Answers (6)

anna_linden
Active Participant
0 Kudos

Hi Anoop,

this is currently not supported as a standard feature. The copy operator could be a short-term solution as mentioned above.

However, this is a key requirement on the IBP for demand roadmap that we are heavily focussing on.

Best Regards,
Anna

thamizhchelvan_gunasekara
Active Participant
0 Kudos

HI Anoop,

You may try to use copy operator function for your requirement, but not standard not straight forward one.

BR

Thamizh

0 Kudos

Hi Anoop,

I think as of now there is no realignment feature available in IBP.

Thanks

hari

Former Member
0 Kudos

Hi Annop,

It can be done in S&OP but as per my knowledge there is no feature of Re-Alignment in S&OP.

We have the same concept "Reference Sales" in our implementation where client want to use the sales of one product and write the values into New product for further forecasting.

It is bit complex but we achieved by making some transformations.

Regards,

Pradeep.

anamika_mudgal
Participant
0 Kudos

Hello Anoop,

Re-Alignment is not supported in SAP IBP.

Thanks,

Ana

0 Kudos

Hi Anoop

Atleast as of release 5, I dont think realignment was supported.

I heard realignment was done outside of S&OP.

Things might have been changed now...but am not sure.