07-02-2016 12:34 PM
Hi,
I have done the configuration that that at the time of Cost Centre PO creation, no fund management document will be created and at the time of Invoicing it should be created, this is OK but i am facing the issue in this case.
PO - 10,000
GRN - 1000
Invoice - 1000
Now the FM document created
PO - + 10000
- 1000
GRN - No document
Invoice + 1000
So ultimately my Budget consumption is 10,000 but i need it should be only 1000.
Please help guys.
Regards
Ajay Goel
07-04-2016 8:40 AM
Hi,
PO is creating commitment in the system and consumes the budget by default. If you want to avoid it, you have to define this value type '51' as 'statistical' in enhancement of update profile via OF39 transaction.
Regards,
Eli
07-04-2016 12:48 PM
Thanks Eli, but I want to avoid only Cost Centre PO. Is it possible?
Regards
Ajay Goel
07-04-2016 1:26 PM
Do you post to the same fund centre/commitment items, as for other POs?
One of the possibilities is using BADI FMAVC_ENTRY_FILTER exempting the entries from AVC control. It will still create commitment,but won't perform budget check.