We are implementing SAP PS module and will need to do soft booking (reserve) of some resources for a project.
It is possible to do this and how it can be done, at a project level. The "split dispatched" indicator (network activity level) can an option to have this requirement?
Thank you,
Hi,
Please explore SAP MRS for this requirement.
Process Variant Overview for Contact Person Process - SAP Multiresource Scheduling - SAP Library
This link will be useful.