on 06-28-2016 6:56 AM
Hi All,
Can anyone tell me if I have created project so when ever I create project and before assigning budget on multiple project I have to run 'CJBN'? is there any other way that it will run background or run only once for all project?
Regards,
Faizan
Hi Faizan,
Go through below link, this might be the exact thing you are looking for.
Regards,
Sid
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Faizan,
You should go through the concept of Budget Availability check in WBS element. You can configure to have AVAC activated during Budget allocation in Budget profile.
Suggest you to search SCN, has these information was already discussed with respect to configuration and even we have documents for the same.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.