Can BOBJ replace BW when ECC moves on HANA

Former Member
0 Kudos

Hi

I plan to move my company's ECC server on SAP Hana database and use BIP/BOBJ 4.2 for reporting.

By using this strategy can i get rid of BW system and use BIP/BOBJ 4.2 system replace BW for reporting purpose.

Regards

Tushar

Accepted Solutions (0)

Answers (1)

Answers (1)

lucas_oliveira
Advisor
Advisor
0 Kudos

Hi Tushar,

(I'm assuming you're asking if that's a good idea or if its possible to do that)

Some very simplified BW scenarios can surely be ported to Suite on HANA.

BW scenarios with stronger complexity (harmonization between many system types and layers) will definitely require a thorough project in order to analyze the impact or such change.

However, I think  the first question is: why do you need to 'get rid' of BW?

I suggest you to start off reading

As well as https://blogs.saphana.com/2015/07/06/sap-hana-replace-bw-hint-no/.

BRs,

Lucas de Oliveira