on 06-27-2016 6:02 AM
Hi all,
In an activity , I am giving the work : 100 m3
Plan values : Activity price planning (KP26) i am maintaining as Rs 300.
When i confirm the activity my plan values only becoming my actual values.
For suppose , by the time confirming the my activity , My actual value is Rs 350. how can give ????
Condition: I should not change my plan .. Because i will use this plan values and actual values in progress analysis.
Best regards,
Mahesh Kumar T
Hi saurab,
In case give the budget to WBS .
Currently One WBS is having multiple activities. This is called high level .
Option 2: Assign one WBS to one activity. then you Can control at minute level .
It depends on your client . if he want more control then he should work more.
BR
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Maria Sir,
Can I place any check on system such that actual cost on WBS does not exceed its planned value.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sir,
Budget control can be made. but this is manual intervention.
Technically budget can be given of any amount i.e. beyond planned costs.
I want technical restriction from system .
Sir, In the same manner as i mentioned before,
Can we have restriction on budget provision beyond planned costs. (through system)
Hi Mahesh,
You should be confirming the hours in the activity, i dont understand what do you mean by 100m3.
You plan 10 hrs of work, as per the activity planning, 1 hr = 100 Rs. So your plan is 1000 Rs.
When you confirm the work, you need to increase the actual hours from plan hours, if you took 11hrs, on confirming system calculate the cost as 11*100 = 1100
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Maria ,
Exactly... You got my point .
Work = 10 hr , Planning rate (Manpower) : Rs 100
Now my working hrs are not increasing. my man power cost only increased to Rs 120.
Since my worker is demanding me for price hike.
Total plan cost : 10 * 100 = Rs 1000
Total actual cost : 10 * 120 = Rs 1200
Best Regards,
Mahesh Kumar T
Hi Mahesh,
Kindly share your screens
" "
Regards,
@KRK@
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
104 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.