on 06-24-2016 7:55 PM
I have an issue where 2 routes, which are identical except for the route name, are presenting with different delivery dates based on which route is used. Both routes are equal to 3 days, and are assigned to the same factory calendar. The calendar is set up with Monday thru Friday as workdays. When route TRK003 is used, it calculates correctly and does not include the weekend when calculating delivery date. For some reason, when the other route is used, weekends are included in calculating the delivery date.
I have compared factory calendars and holiday calendars in ECC and SCM. I have regenerated time periods via /SAPAPO/CALENDAR and I have re-transferred global settings for factory calendar via RSA1 in SCM. Also, I have checked entries in TVRO and they are the same.
Neither route is new so it's unclear why this has started to happen. The only thing to occur recently was a scheduled outage for ECC and SCM for an Oracle upgrade. Coincidental, or not, the issue was brought to my attention the week after the outage. I have been unable to find comparable SAP note(s) so I have logged this with SAP. I thought I would reach out to the gurus as well.
One possible reason that I can think of is - may be your Pick/Pack time or Loading Time is different for your routes TRK003 & CSL003.
Have you checked the setting IMG|Logistics Execution|Shipping|Basic Shipping Functions|Scheduling|Delivery & Transportation Scheduling|Maintain Duration.
Within that, I would check the Pick/Pack time & Loading Time to see if they are set differently per your routes.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
10 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.