on 06-22-2016 5:47 AM
Hi Expect,
During the ATP check at sales order creation level, the system should need to pick the stock from the supplying plant and propose the schedule line date according to the special procurement key. This leads to an incorrect delivery date in the schedule line. My requirement is
I understand this is not the standard way. Please let me know if any customize solution or enhancement to solve this required.
Thanks,
Raj
Have a look at OSS note 1644443 and consider any of those enhancements given in the said note.
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank you so much for this solution. I understand this user exit will helpful for the delivery date but still need to figure out the stock transfer from supply plant to dispatch plant.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.