on 06-17-2016 4:05 PM
Hi All,
We are in the process of integration of batch master creation in GBT system.
In ERP system, we have used batch level at material.So Batch number are created based on material level.
But when I trying to send BATMAS IDOC to GBT system, we are getting the error as
Please guide us the procedure to overcome this error.
Thanks
KB
Hi KB,
could you please check if you already registered the system and the corresponding RFC connections in transaction /GBT/LOGSYS_CONFIG (Configuring of connected logical systems) in SAP GBT?
Regards, Christoph
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi, K B,
Please use Report: /GBTINT/R_SEND_BATMAS to send BATMAS IDoc from ERP.
If your batch level setting is on material level in ERP, your batch IDocs shall also be sent on material level. Analyzing from the error messgae, your batch IDocs are generated on plant-level. Why does it happen? You need to check whether it is the right client? Did you send IDocs by the correct report? Using the above named report, the error shall be avoided.
Best regards,
Lilly
This caused due to config.Thanks for guidance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.