Could any one tell the logic how it works for rescheduling for Delivery Date of Earliest Schedule Line in V_V2 so we could do  process Rescheduline based on Materaila availibility

Thanks

Santosh

Accepted Solutions (0)

Answers (3)

Answers (3)

Lakshmipathi
Active Contributor
0 Kudos

You have already opened a discussion and are getting responses here

Opening another thread with the same subject is not encouraged in SCN.  Adhere to RoE

G. Lakshmipathi

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Implement SAP Note 1917266 and Note 1897242.

Then you will have Business Add-In "SD_ATP_SDV03V02" delivered with this SAP Note. This Business Add-In is contained in the composite enhancement spot ES_SD_ATP_RESCHEDULING.

Best Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Brahmankar,

could you please let us know where to check of REPORT note_1917266 its quite long , i am not sure that its has the details of Rescheduline based on Materaila availibility that needs to be done in V_V2.

if yes... could you let us know in exact place.

Thanks

Santosh

n_soni
Participant
0 Kudos

Santosh,

-System does a forward scheduling if backward scheduling is not configured (mark “blank”on configuration)

-System does not do a forward scheduling if replenishment leadtime is set up

-System does a forward scheduling if material availability date is in the past

-System does backward & forward scheduling automatic and this is rescheduling.

you can double check your system configuration

IMG -> Sales and distribution -> Basic functions -> Availability check

we can only prioritize in V_V2 depending on

1. Customer priority set in shipping tab under delivery priority

2. Customer - Material info record

3. Date of order creation

4. Delivery date on the schedule lin level

5. Document Number and

6. Document Date

If std prioritization is not enough then enhancements (userexit/BADI) can be implemented based on client requirement with help of development team.

Also refer previous thread for more details - how to configure rescheduling for sale order qu... | SCN

Hope this helps.