Hello Friends,
I have a general query regarding AVAC, I have set AVAC on the annual release budget with activation type 1. Requirement from business is user is not allowed to generate the PR/PO until budget is release.
Now, Budget is not released yet. But, although AVAC gets activated during budget allocation for release budget, user is allowed to create PR/PO. I am confused with this system behavior.
Is this standard behavior of SAP? If yes how could we stop user to do so?
Regards,
Omkar
Hi Omkar,
Kindly refer below OSS notes:
2257155 & 2263077
And also kindly do refer below threads
1. Prevent release of wbs-element before budgeting:
http://scn.sap.com/docs/DOC-60778
2. Budget functionality in Project System:
http://scn.sap.com/docs/DOC-34141
Thanks,
Vivek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Vivek,
Thanks for you reply...
1. Prevent release of wbs-element before budgeting:
http://scn.sap.com/docs/DOC-60778
This docume t contents very informaive information.
Regards,
Omkar
Hi Omkar,
Is the AVAC activated before or after creating PR ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Can you confirm the activation type in the budget profile being maintained (OPS9). It should be 1 if AVAC is activated automatically for your WBSEs.
Please ensure that this same budget profile is maintained in the subject project.
Also ensure whether budget was distributed and released on the specific WBSEs for which AVAC did not get activated.
Regards
Shubham
Dear Terence,
I agree with you, system should give me error while PR/PO posting if budget is not released. but system is allowing me to create PR/PO even though budget is not released.
Example
WBSE system status REL, BUD, AVAC
Budget Rs.100.00 (CJ30)
PR Rs.90.00 (ME51N) Committed Rs.90.00 in Budget
I have also checked that after budgeting through CJ30, AVAC gets activated on the WBSE.
We are working on Annual Values.
Regards,
Omkar
Hi Shubham,
As WBSE is released, user status automatically set to RLD (Released) status which allowed to create PR/PO. I dont want to stop them to create.
But my query is if the budget is not released then user should get error Message for budget exceeded.
User is not getting any error for the same...
Regards,
Omkar
Hi Omkar,
I feel this is because of the budget profile configuration.
1. Activation Type - 1 (Automatic Activation during Budget allocation)
2. Releases
Both are contraditory, you are activating AVAC on two places, so that system uses Activation Type 1 as precedence and allow you to maintain PR/PO.
Try to Uncheck the releases and see the behaviour
Regards
Terence
Hi Terence,
I have checked it, seems no difference to me right now. It is allowing to create PR/PO up-to budgeted amount, whether i have checked Releases or unchecked.
Rather I tried with user status too for BUGD only Budgeting and Budget release is possible, financial postings and commitments are blocked. This user status set with System Status BUDG. Later user status RLD which Activates with System Status REL for WBSE.
but there is no automated user status update for Budget Release as shown in above image and doing is manually for all those WBSE is a big task.
I want user should get error while creating PR/PO as Budget is not released.
Please suggest your views on this..
Regards,
Omkar