on 06-14-2016 3:43 PM
Hi All,
Actual values in report S_ALR_87013558 for particular WBSE does not match with values in Actual Cost Line Item report CJI3.
As far as I am aware actual values in S_ALR_87013558 is calculated based on GRN(P/Q)+Direct FI postings. When I use this as reference and check the MIRO documents & FI postings these values does not match with actual values in standard report S_ALR_87013558.
Please correct me if I am wrong & also let me know if there is any other way to make sure actuals in standard report 558 is correct.
And Commitment values in report S_ALR_87013558 are perfectly matching with Commitment line report CJI5 for particular WBSE.
Thanks & Regards,
Kumar
Hi,
Are you able to identify the missing cost from 558* and CJI3 report ?
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to find out the which type of cost is missing, like Labour / Material etc. Compare based on period / amount etc
Then it will be easy to trace down back.
558* has lot of issues and lot of fixes with SAP, so before we search for a fix, we need to make sure, what type of cost is missing.
This analysis will help, whether its an issue with Form, standard SAP or any other
Regards
Terence
Hi Kumar,
you can search SCN for same type of issues exist and very well replied by SCN members.
S_ALR_87013558 & CJI3 not matching | SCN
cji3 and s_alr_87013558 not match | SCN
https://scn.sap.com/thread/1555500
and many more.
thanks
Sunil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sunil,
Thanks for your response, I have checked the above mentioned threads but for the issue I am facing these are not helping.
I have checked the cost element for which actuals are posted via CJI3 & then checked for value category assignment in FS00->edit cost element there I can see correct value category 1(primary cost) & 11(revenues) respectively.
So please let me know if there is any other customization for value category to cost element.
Thanks & Regards,
Kumar
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.