Hi Experts,
I am not able to copy basic date to forecast dates from path Edit--->dates--->Copy basic to Forecast as the option is disable , please advise.
Regards
Abhishek Singh
Hi Abhishek,
As standard behaviour, this option is available only at network level, not with WBS element
If you select network, it will be highlighted
If you select WBS element, it will be greyed out
Regards
Terence