Not able to copy basic dates to forecast date for WBS

0 Kudos

Hi Experts,

I am not able to copy basic date to forecast dates from path Edit--->dates--->Copy basic to Forecast as the option is disable , please advise.

Regards

Abhishek Singh

Accepted Solutions (1)

Accepted Solutions (1)

MTerence
Active Contributor
0 Kudos

Hi Abhishek,

As standard behaviour, this option is available only at network level, not with WBS element

If you select network, it will be highlighted

If you select WBS element, it will be greyed out

Regards

Terence

0 Kudos

Hi Terence,

Thanks for this knowledge, You are always been a life saviour to me:)

Can you please tell me that how can we use this functionality as Network does not have any Forecast date and how this will impact associated WBS dates.

Regards

Abhishek Singh