on 06-13-2016 8:00 AM
Hello,
we have double firm planned orders in ECC for example planned
order one order for material.
In APO this planned order has no requirements on it BOM components, so
this planned order doesn't create demands for the BOM components and so
the BOM components are not planned in APO.
In ECC this planned order for example order **** contains BOM components
are creates in ECC demands on the BOM components.
So we have a different behaviour, APO plannes less than ECC requires.
There are several double firmed planned orders for which this issue is
true.
Request to Please check and suggest me if anyone faced the same issue.
Regards
Deepika Kukreja
Hi all,
Thanks everyone. This issue is closed.
The problem is with our Enhancements so we corrected it.
Regards
Deepika Kukreja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepika,
We have faced similar issues, it is an issue with incorrect CIF post processing. I suppose you have this issue after the overnight batch jobs. In case the deletion orders are not processed and you have subsequent order getting generated there is a possibility of this kinds of issue.
Kindly check your CIF configuration and the CIF post processing.
Regards
Sasi