Hi ,
Question 1:
We have CIFed recipes with classes(work center class 019) assigned to operations and have alternate resources (as alternate modes) in the PPDS PDS. Both the modes have the same fixed and variable capacity consumption, is there a way to change the capacity consumption rates for the alternate resource?
Question 2:
While executing the production planning heuristics, if there is an overload on Resource 1(Mode A, with priority 1) ; will it automatically schedule the planned order on the alternate resource(Mode B,with priority 2) , if yes , how can this be achieved ?
Please shed some light on this.
Thanks,
Rajan.
Hi Rajan,
In case of Alternative Resources with Work Center classification, only by BAdI can the processing times of the alternative modes be modified (during PDS transfer).
If Alternative Sequences are created in the Routing, there is a BAdI solution in an SAP note that allows to transfer them to APO, and in this case the operation durations are translated to the alternative modes as maintained.
Also, given that PP heuristics (SAP_PP_002) are mostly used with Infinite Scheduling, overload in a given mode will not automatically cause the activity to shift to the other mode. This can be achieved later on with DS heuristics. One remark here is the fact that the system will not choose the mode with highest priority, but rather select the fastest mode (e.g. an activity takes 60s with Mode 1 Priority A and 45s with Mode 2 Priority B - if both resources are free, Mode 2 Priority B will be chosen).
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.