Difference Between Expiring Qty' and 'Projected Wastage Quantity KF

Former Member
0 Kudos

Hi,


I cannot understand what the difference between the SAP standard key figures: 'Expiring Qty' and 'Projected Wastage Quantity'? can anyone explain?


Thank you

Alexander

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Alex

Please find the macro definitions for both the KF.

●  Expiring Quantity

Displays the total quantity of stock or receipt elements in a bucket that are no longer usable from this bucket on.

●  Projected Wastage Quantity

Displays the portion of the quantity displayed in key figure Expiration Quantity that needs to be discarded in the current demand situation.


As you can see below, in Projected Wastage Quantity it would also consider the demand requirement till the expiring date and provide you remaining quantity which could be strapped. Projected Wastage Quantity is more like dynamic KF which could change based on demand situation.


Please let us know if this information helps you.


Thanks

Amol

Former Member
0 Kudos

Hi ANOL,

Thanks for your respond, but can you please give an example ?

Thank you

Alexander

Former Member
0 Kudos

Hi Alex

For example, you have stock of 1000 Qty which is about to expire on 31 Dec 2016, then ideally you will see 1000 Qty Expiring Quantity. But if you total demand of 800 till Dec 2016 then you should see only 200 as Projected Wastage Quantity Qty.

Please cross check from your side and close the thread according to

Thanks

Amol

kenneth_snyder
Active Contributor
0 Kudos

Amol,

You are a very patient man.   Very kind.

Alexander should read the information you gave you and tested it to see what the differences are.

Ken

Former Member
0 Kudos

Hi Amol,

Thanks for your help.

Regards,

Alexander

Former Member
0 Kudos

Hi Alex

Can you close the thread according to How to close a discussion and why

Amol