Hi All,

I am working on the feasibility of installing PO 7.4 in our project.

Our Current landscape includes the following systems that need to be connected to PO 7.4

  1. ECC 6.0, Enhancement Pack 1, SPS 7 (SAPKB70107)
  2. CRM ABAP 7.0 EhP 1, SPS 7 (SAPKB70107)
  3. SAP BW 7.0 EhP 1 for SAP Netweaver 7.0

Please let us know if any upgrade is needed in the connected systems as a prerequisite of PO 7.4 installation.

From the SAP Upgrade Dependency Analyzer I cannot see any need for upgrading the version or service packs in ECC or CRM.

Please provide your inputs on this.

Thanks,

Amrita

Accepted Solutions (0)

Answers (2)

Answers (2)

mate_moricz
Advisor
Advisor
0 Kudos

Hello Amrita,

If you have run the SAP Upgrade Dependency Analyzer and found no problems then there is no need to upgrade. For more information check SAP Note 1406261.

PO will be be able to handle to connect the systems.

Regards,

Mate

former_member186851
Active Contributor
0 Kudos

Hello Amrita,

I guess there wont be any problem because of these packages.

You can try configuring one scenario and test it end-end.