on 06-01-2016 10:28 AM
Hi All,
Planned order created by SNP run (CTM) always has start and end date same in ECC and in APO both start and end date is different.
The same planned order when we check in ECC same order is having different end date from APO.
There is one month of difference in ECC in end date as compared to APO End dates in planned Orders.
Example:
Planned Order Start Date End Date
In APO 19/06/2016 20/07/2016
In ECC 19/06/2016 19/06/2016
In PDS, activity duration (fixed) is 13 day for setup and handle.
Please provide the info what could be the reason for SNP planned order have not the same end date as APO in ECC.
Let me know if required any information to understand the facts.
We have also ran the scenario with Heurstic planning run but no change and faced the same date issue in ECC and APO.
Regards,
Deepika
Hi All,
We don't have any issue with CIF, I tried Re CIF of all data.
No issues with calendars.
Even I Tried in the Debug mode able to find that planned orders moving to ECC and having correct date in APO and while going ECC it is changing. Its using standard FM but still not able to find how its changing Date while CIF.
Regards
Deepika Kukreja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check whether the APO Production calendar is in sync with ECC.
Try executing CCR.
Just my thoughts
Vinoth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepika,
Could you please try to re-CIF the master data from ECC system like PDS/PPM.?
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Deepika, With the information you provided, it looks like Planned order dates were manually modified in APO & that change hasn't reached ECC? Sounds familiar? or Was the planned order in APO anytime had a 10/06/2016 end date at all? before changing to 20/07/2016? or was it at the creation itself..the dates were mis-match..
Thanks,
Uthaman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.