on 06-01-2016 8:32 AM
Hi
Please advice for requirement is as
Qty Contract (Zcq1) with validity from 25.05.2016 to 31.05.2016 for 10 qtl and sales order generated on 01.06.2016 , (one day late)
A condition (zsur) should be auto fall on the base of late order and quantity
Thanks
Hi,
most probably you will need a vofm requirement checking if it is late and a fomula for zsur calculating the value based on days late and qty.
BR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,'
How are the condition records dates maintained in the system.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.