on 06-01-2016 7:39 AM
Dear All ,
Above warning message appear while assigning budget by CJ30. We have Controlling Area currency INR & Company code currency AED . So done budget profile as below . Project currency is also AED.
Its till allow me to Save the budget but not understand why this message is appear . Check all related configuration setting & also on SCN but no suitable answer found . Let me know if anyone face such issue .
Thanks
Virendra .
Hi Virendra,
Refer below note for more information
1245966 - Activating the availability control for activation type 1
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Maria,
Thanks for reply,
This note is applicable if your AVAC not activating for WBS , but in our process AVAC is activated for WBS but till system showing this message . Please check the screen shot of WBS & Assigned budget
Didn't understand why system showing such message that suitable budget , what is meaning of Suitable Budget ?
Thanks ,
Virendra.
Dear Maria ,
Yes same message was seen while assigning budget as you shown . Now means I have to set OVERALL check box also in Availability control in budget profile ? . Because if you seen my first screen shot OBJECT CURRENCY check box is ticked & now I have set 'overall' check box also ?
Thanks ,
Virendra