Hello Experts,
when CIFing workcenter from ECC to APO, no values are put in the Planning parametrs tab in APO resource tab, capacity header in workcenter.
But still a value -30 to +180 days is being populated in APO resource as validity. Where is this value coming from ? any setting in ECC or APO ?
also there is days in past and future mentioned in CFC9 setting in ECC . what is this used for ?
Regards
Alin
Hi Alin,
In APO, there is database table /SAPAPO/RESLCT. If there are entries in this table, these will be the default Days- and Days+ of the Resource. You may adjust it so it fits the values from CFC9.
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alin
As per Expert Tiago Furlanetto the values are mantained in database table /sapapo/reslct .
You need to maintain single value in the table as per sap note note 449452,
Regards ,
Virender
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Alin
In work center header you have APO resource key. I think here you can define the planning parameters. If you don´t define the planning parameters I think they will pick it from CFC9 settings in ECC. If you don´t maintain the information here, I think by default system will pick 30 days in the past and future.
I hope this information will help you.
Amol
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.