Hi Experts,
I have an issue with synchronization of data between WBS elements (Project Definition) and the PPM project.
I have seen that there is the option in DFM
to map certain fields of project definition (WBS) and PPM project definition but after saving the data in CJ20N the data in PPM is not updated. When I change data on the PPM side it is being transferred to PS correctly.
Another thing that is confusing for me is that there are two places to assign fields between PS and PPM:
and:
Do you know what is the difference and where should the changes be made?
I cannot see the difference between the both options ( programs SAPLDPR_MAPPING_VIEW and SAPLINM_SYNC_FRAMEWO ).
Dear Emil,
Information concerning the synchronization from PS-project to Item can you find in Wiki under:
Decision Flow Management (Tips) - Product Lifecycle Management - SCN Wiki
best regards,
Judith
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Judith,
Thanks for the response!
What I find particularly interesting is that in the table INM_OBJGRP_SYNC I can only find the following entries:
I guess that this table lacks grouping SOURCE_GROUPING (PD)- TARGET_GROUPING (PDCP), SOURCE_GROUPING (PDCP)- TARGET_GROUPING (PD), SOURCE_GROUPING (PR)- TARGET_GROUPING (PDCP) and SOURCE_GROUPING (PDCP)- TARGET_GROUPING (PR).
Do you know if in standard solution is it possible to enter these conections?
Dear Emil,
DFM Synchronization isn´t available for data transfer from Project Management Project to PS-project.
It´s available from Portfolio Managment to PS-Project or
Portfolio Management to Project Management Project or
within Portfolio Management (Initiative to item,...)
See Online documentation:
Best regards,
Judith
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.