on 05-25-2016 6:32 AM
Hi All,
I have created project on which I have assigned material and release it.That material already have PP BOM and routing so after running MRP for planned order, I get planned order but within that order, account assignment category is missing so kindly tell me where I'm missing? in config or master?
Regards,
Faizan
Hi Faizan,
1.copy your PP BOM to WBS BOM
2.Use the BOM transfer ..(CN33)
3.Run MRP MD51
Hope this process will help you .
Regards,
Mahesh