Year's Days at Price Level

Former Member
0 Kudos

Hi,

How to define 365 days in Year at Price Level, By default its taking 360 days in Year (In Time Base price )

But its taking 365 days default in Quantity base price. Please suggest .

Yatendra

2 REPLIES 2

0 Kudos

Hi Yatendra,

Can you be little more specific about your scenario ?

Viz., what is the Time category you maintained ?

Thanks

Tatha

0 Kudos

Hi Sir,

Fix charge slab is 

0-300 KWH -> 225 / KW  per month

300-1000 KWH -> 250 / KW  per month

1000 to last KWH  -> 275 / KW  per month


So Please suggest how to make  the price or any other standard way for get Fix charge on the basis of energy consumption ?