on 05-19-2016 2:07 PM
Hi gurus,
I am wondering how to schedule the activity of testing a manual control offline, I mean using AIF. Could you please help?
Thanks,
Kind regards,
Hello John,
You will need to activate them through SPRO.
You should tick the checkbox in the SPRO customizing “Configure OWP Business Scenario”. There you can select what category you want to send the offline test. Afterwards, schedule a normal test and it will go to the user with a PDF attached.
Regards,
Fernando
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.