on 05-19-2016 1:57 PM
http://help.sap.com/saphelp_sm71_sp10/helpdata/en/34/65945176483620e10000000a423f68/frameset.htm
Hi,
i have configured SAP PPM with Integration Charm like mentioned in the following blog.
PPM Projects intergration with Change Request Management as of 7.1 SP10
The only thing which doesn't work is the timesync between the Charm Projekt and the PPM projekt. Can you give me any hints.
Report DPR_CATS_CPRT_TRANSF says ID Project with project type 000000001 does not allow confirmation for the Task.
Thanks in advance.
Solved on my own.
The report Needs the following customizing:
spro->projectmanagement->structure->define Project Types->mark field CATSSRMFIN with X an TimeRec.f. with Tasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
13 | |
13 | |
11 | |
11 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.