on 05-17-2016 2:45 PM
Hi Experts,
Could anyone help me that I am "Not able to see PO ESR objects in ECC`s sproxy".
As per our Basis team Connectivity between SAP ECC and SAP PO is everything fine.
Regards,
Sateesh.
Hi All,
Thanks to everyone for your valuable Suggestions/Solutions.
Now I am able to see objects in sproxy.
we are also not sure how it was resolved, last step which we performed is providing the necessary roles for the users which are used in th SM59 RFC destinations.
Configuring Process Integration After Installation - SAP Library
Now we are getting another error, when we tried to trigger one message to the proxy (PO to ECC) we are getting below error:
Transmitting the message to endpoint <local> using connection AFW failed, due to: com.sap.engine.interfaces.messaging.api.exception.MessagingException: com.sap.aii.af.sdk.xi.srt.BubbleException: HTTP Response Received. Status Code = 500 [null "null"]
Regards,
Sateesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Please close this thread as the new issue is not relevant to the original question triggered.
Also when raising a new Thread do make sure your question has all relevant info. Current info provided will lead to more questions like what is your configuration? Did you configure ICO etc? Please share as much details in your question as possible to ensure folks responding have info data to respond to.
And finally, if you use the current error and search, you will find multiple responses for same issue.. Until you want to end up with a bunch of threads to read into, do provide more specifcis around the issue.
Regards
Bhavesh
Hi All,
Can anyone provide end to end configuration steps so i can cross check whether the Basis has followed all steps or not?
Regards,
sateesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sateesh,
Please check the below in ECC system.
1. In SM59, the RFC connection "SAP_PROXY_ESR" of type "G" created and working.
You should provide the PI system name, port and "/rep" as path prefix.
Also make sure the user used in this connection has the required roles.
If something is changed here, recreating the connection will work.
2. In SLDAPICUST, you should have the PI system name mentioned as primary and test connection working.
3. You should have the business system for ECC system present in the PI SLD and when you do SLDCHECK in ECC system you should be able to see that BS.
4. Make sure the ECC business system in PI SLD has a logical system name associated.
Best Regards,
Priyanka
Hi All,
Before we din't have the proper roles for users which are used in RFC destination of ECC now we have assigned the roles as per the below link
Configuring Process Integration After Installation - SAP Library
After assigning roles anything we need to do to show the ESR objects in sproxy.
Regards,
Sateesh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Satheesh,
Is it a single stack?
Check in SM59 connection in addition to notes provided by Inaki.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sateesh,
Check these notes
2266714 - PI ESR objects are not visible in SPROXY
1528587 - PI ESR Content Objects are not visible in SPROXY
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
10 | |
9 | |
9 | |
9 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.