Activity Element Auto confirmation

Former Member
0 Kudos

Hi,

Is it possible to do activity element confirmations automatically when doing activity confirmation. Or system should restrict confirmation of activity unless activity elements are confirmed.

Thanks,

Harsh.

Accepted Solutions (1)

Accepted Solutions (1)

Paulo_Vitoriano
Active Contributor
0 Kudos

Hi Harsh,

Seems like a simple test you can easily run yourself...  I would expect the top-down logic, if you confirm activity, elements will be also confirmed.

Regards,

Paulo

Former Member
0 Kudos

Hi,

I have checked. Activity is confirmed but element are not.

Thanks,

Harsh.

MTerence
Active Contributor
0 Kudos

Hi Harsh,

In CN25, try to do Summarized Confirmation, which will confirm the activity elements assigned to the activity.

Regards

Terence

Former Member
0 Kudos

Hi,

With summarized confirmation i am able to confirm activity elements automatically but the work associated to activity elements is not updated.

Thanks,

Harsh.

MTerence
Active Contributor
0 Kudos

Hi Harsh,

Just now, i observed the similar behavior in my system.

I guess you need to explore user exit and to confirm the activity element, or you can use CN47 and do collective confirmation.

Regards

Terence