Hi experts,

I am working with EGR process .

After creating inbound delivery in ewm ,I didn't found inbound delivery document in ecc.

Once Inbound delivery is created in ewm system shall create inbound delivery in ecc ? Isn't it ?

thank you

srini

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hello Srini,

Please check the inbound queues in ecc.

If any queue exists for that PO/ID clear it and check the PO history.

It will updated.

BR,

Olet

former_member183610
Active Contributor
0 Kudos

Hi Srini,

Once IBD is created in EWM , that should be update in the ECC system.You can find the IBD in the PO.

If you are not getting the IBD in ECC, please check the queue monitors in both systems.

GRN is the 'code for initiator communication chain ' to create inbound delivery in ECC with reference to EWM document type 'EGRE'.

and also check the 'Mapping of ERP Item Type'.standard is EL+ELN to EGRE+EDLV

you can find the integration in below paths

img-SCM Extended Warehouse Management-Extended Warehouse Management-Interfaces-ERP Integration-Map Document Types from ERP System to EWM

img-SCM Extended Warehouse Management-Extended Warehouse Management-Interfaces-ERP Integration-Map Item Types from ERP System to EWM.

BR,

C K Reddy

former_member183610
Active Contributor
0 Kudos

Hi Srini,

In addition to above reply. If you process physical goods receipt through '/SCWM/GRPE'. you can get the below message after creating IBD in EWM.

one inbound delivery can be updated in confirmations tab of the PO in ECC.

BR,