on 05-16-2016 7:06 PM
Hi All,
We are facing an issue with fixing of orders in detailed scheduling planning board.
When we right click on order and select --> fix, the graphical representation does not appear correct i.e. there is no red line appearing on order which indicates the order is fixed.
However, if we see the details of order (either in planning board or product view)- its actually fixed.
As per my understanding, it seems like the issue is with graphical objects in planning board. But this is not happening for all the orders.
Has anyone seen such situation earlier. If yes, please share the details.
Many thanks,
Aditi
Hello,
Is the issue resolved when you save or refresh the data in the planning board?
If not, you can analyze the steps of the decision table for graphical objects (/SAPAPO/CDPSC2 > Click on the Planning Board Profile > Charts > Resource Chart > Decision Table for Graphical Objects) and see if the object that is referenced is the expected object in the planning board.
Regards,
Yasmin Alayyan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Yes the fix indicator is set for an operation and the orders appears as date fixed in product view as well as planning board.
But the graphical representation does not indicate that its fixed(horizontal red line on the order).
We are not using standard overall profile(SAP001) but yes the profile created for DS board is copied from standard overall profile.
Regards,
Aditi