on 05-16-2016 11:16 AM
Hi,
I have a project with plant assigned as A at project definition level. I have released my project,created purchase requisitions against the project and now i need to change the plant to B. I have tried in IDES system, i can able to change it. But is it recommended to change the plant? What are the best possible ways to implement this scenario?
Regards
Gouthami
Hi Gouthami,
In standard, system will not restrict you for changing the plant, there is no issues, so you can change it.
You cannot change the plant in Network, after it is created.
Regards
Terence